10) New Orleans Project: November 2009 - April 2011

  • (1) Application: CI-CMC

  • (2) Purpose: To prevent landslide and settlement during raising of levee

  • (3) Quantity
    Number of Elements: 7,931
    Section of Element: φ5.25ft (1.6m) column x 2 axes
    Installation Depth: 59.4ft (18.1m) to 67.3ft (20.5m)
    Total Installation Volume: 921,453cy (628,046m3)

  • (4) Clients
    Owner: US Army Corps of Engineers, New Orleans District
    Prime Contractor: Archer Western - Alberici, JV in Alliance with Treviicos
New Orleans Project: November 2009 - April 2011
New Orleans Project: November 2009 - April 2011